Motorway · BOT project company
Ankara–Kırıkkale–Delice Motorway
Coordinating plans, institutional interfaces, title work and construction priorities through an approximately 25-person organisation.
Project context
Responsibility, method, contribution.
A 120 km project with around 4,200 parcels contains too many technical and institutional dependencies to manage as disconnected lists. I aligned acquisition delivery with the construction team’s priorities.
My contribution
- Coordinate technical, valuation, negotiation, legal and title-registration teams.
- Complete plans and necessary case initiations for roughly 100 km of mainline as a team within approximately ten months.
- Bring around 60 km to a level at which construction could start through permitting, title and consent work.
- Lead the AKDOGIS project developed with Esri Türkiye.
Digital approach
AKDOGIS was developed to review three-dimensional design, parcels, acquisition status and multidisciplinary project information in a shared GIS environment. My focus was on making the system answer real project needs.
A lesson from the work
A kilometre included in an acquisition plan is not automatically a construction-ready kilometre. Progress needs to be reported alongside the completed steps that make field access possible.
This account follows the responsibilities and project scopes in my career record. Figures describe relevant assignments or team work, rather than a claim of sole personal production.